Construction Projects

CSAH 29 & 33: Reconstruction Project

CSAH 22: Bituminous Reclaim, Culvert Replacement & Bituminous Pavement

  • Purpose of Project: Address pavement & culvert deterioration
  • Project Location:
    • CSAH 22 – CSAH 11 to CSAH 14
  • Construction Start Date: October 1, 2018
    • Road Closure start date October 2, 2018.  
    • Expected to last 14 days, weather dependent.  
    • Construction in 2018 is expected to last until November 2, 2018 (weather permitting).  CSAH 22 will be gravel for the winter with the bituminous pavement to be placed in the Spring of 2019.

CR 58: Bituminous Reclaim, Culvert Replacement & Bituminous Pavement

  • Purpose of Project: Address pavement & culvert deterioration
  • Project Location:
    • CR 58 – CSAH 3 to CSAH 4
  •  Construction Start Date: October 4, 2018.
    • Road Closure start date October 8, 2018.  
    • Expected to last 8 days, weather dependent.
    • Construction in 2018 is expected to last until November 2, 2018 (weather permitting).  CR 58 will be left gravel for the winter with the bituminous pavement to be placed in the Spring of 2019.

CSAH 2: Reconstruction

  • Postponed until 2019
  • Purpose of Project: Address soil stability and safety
  • Project Location:
    • CSAH 22 – 0.5 mile through Little Rock Lake
  • Estimated Construction Start Date: 2019
    • To be coordinated with the DNR Little Rock Lake Draw-down

CSAH 29: Bridge Repair

  • August 29, 2018 News Release
  • Purpose of Project: Repair Bridge deficiencies
  • Project Location:
    • CSAH 29: Sartell Bridge over Mississippi
  • Construction Start Date: September 4, 2018